A large-scale expansion programme creating 462 modern residential cells at the fully operational Category B HMP Rye Hill. The scope included the enabling and groundworks packages ahead of the main build, specifically site clearance, earthworks, utilities, drainage, concrete foundations, haul roads, car parking and soft landscaping.

Client

Ministry of Justice

Location

Rugby Warwickshire

Principal Contractor

Galliford Try

HMP Rye Hill Careys

The works were successfully delivered to programme in a high-security and restrictive environment.

  • Site set up, utility scanning, and establishment of site compound including tarmac haul roads, car parking,
    street lighting, and road signage.
  • Site clearance and earthworks.
  • Installation of utilities including HV, LV and potable water connections, ducts, and a sprinkler base.
  • Main drainage runs and installation of deep drainage, attenuation tanks, and swales.
  • Reinforced concrete foundations and slabs for precast house blocks.
  • Finishing works including kerbs, channel and slot drainage, tarmac, and soft landscaping.
  • Challenging high security environment necessitating extensive engagement with G4S to develop efficient methods without affecting the day-to-day operation of the prison.
  • Regular collaborative logistics planning meetings to proactively arrange all deliveries into site and waste removal from site.
  • Security checks and vetting on all personnel and delivery drivers.
  • Adjustments to delivery standards, processes and ways of working to meet the stringent security protocols required by the prison.
  • Daily searches including physical, vehicle and tool/ equipment check-in and out.
  • Prison escort for personnel at all times.
  • Programme management accounting for prison operations, requirements for personnel escorts, and lockdown procedures.
  • Proactive implementation of contingency plans accounting for the prison environment including a bespoke system for inventory (check-in/check-out) of tools, and procedures in the event of any emergencies, disruptions or deviations to planned operations.

Accessibility Settings

Text

Applies the Open Dyslexic font, designed to improve readability for individuals with dyslexia.

Applies a more readable font throughout the website, improving readability.

Underlines links throughout the website, making them easier to distinguish.

Adjusts the font size for improved readability.

Visuals

Reduces animations and disables autoplaying videos across the website, reducing distractions and improving focus.

Reduces the colour saturation throughout the website to create a more soothing visual experience.

Increases the contrast of elements on the website, making text and interface elements easier to distinguish.