
The project forms part of the wider regeneration of White City, which has seen the area transformed into a world class business and education district.
The specific gas works comprised:
A number of challenges arose during the works. A prime example was realisation that the core in the basement wall was incorrect. This was addressed through a redesign of the fabrication size passing through the core, approved under a variation through Careys’ in-house Utility Delivery Manager and Cadent.
The gas main was installed in two separate phases, PH1 from the live cadent main in South Africa Road into site, and PH2 from the site boundary into the basement. The original information issued proved to be incorrect, setting out detail for the termination of the main in PH1 at the site entrance. As a result, the main had been installed outside of the easement which was not Gateway Central’s land. With the main now live, the team addressed the issue via application for a design deviation and RO (Routine Operation) to move the live main back into the easement alignment. This was agreed prior to PH2 commencing.
The main installed on site (8m) was subsequently moved into the agreed alignment and then extended through PH2 at the same time. This unusual variation was swiftly agreed, largely based upon Careys’ established and trusted relationship and partnership with the provider (Cadent).
The solution culminated in significant cost savings for the client as a typical 16-18 week lead time for these alterations was avoided; the Careys team were able to re-design, seek approvals and mobilise to site in only 10 days, to carry out these essential diversion works.

We'd love to hear from you, so please get in touch