Construction of a new cementitious products importation and distribution facility (annual capacity 730k tonnes) to help meet rising demand for low carbon construction solutions.
After removing/diverting existing utilities, demolishing foundations and obstructions, and installing the pile mat, main civils works consist of: materials handling/processing/storage infrastructure; sitewide surface water management; potable network design and installation; and road construction, external surfacing, and fencing.
Port of Tilbury Cement Grinding Facility is operated under NEC Option A 2017 NEC 4 Option A with secondary options X2, X4, X7, X8, X11, X15, X16, X18, Y(UK)2, Y(UK3) and Z clauses.
We believe that to successfully deliver a NEC Option A contract all stakeholders must place strong emphasis on effective communication and collaboration. This partnership approach is embedded in the contract’s structure and processes to ensure trust, transparency, and proactive problem-solving which ultimately ensures the project is delivered on time and within budget.
At Port of Tilbury Cement Grinding Facility we achieved this collaborative approach through various meetings and workshops including but not limited to;
To encourage communication outside meetings and workshops we operated an “open-door” policy with the Holcim UK, meaning we often would just go and sit with them to discuss any prompt issues and vice versa, rather than communicate over emails.
The primary risk management tool was the risk register, which was produced in detail at the very earliest stages of the project. Led by the project manager, the whole team assessed every facet of the project for risk and opportunity. These were then quantified where possible, assigned owners, and discussed in detail at the first risk reduction meeting to agree mitigating actions.
The register was scrutinised and updated internally on a weekly basis, with the assistance of a third-party design management company, as well as our own design manager and operational team, the Holcim UK reviewed the register during monthly meetings.
Early warning notices and compensation events are critical to the success of NEC Option A contracts as the are designed to manage risk, provide transparency and prevent disputes to ensure the works are completed on time and budget.
To proactive solve issues before they arise our team raise early warning notices as soon as we become aware of an event that could: increase the total of the prices/delay completion/delay meeting a key date/impair the performance of the works/increase contractors cost. Prior to raising an early warning notice our commercial team contact the Holcim UK’s project manager to notify them of the potential and they will briefly discuss the notice . The risks identified in the early warning notice would be added to the risk register, which is reviewed and discussed with the Holcim UK on monthly basis. In between the meetings, Holcim UK and Careys commercial team kept open dialogue via CEMAR discussing best way to mitigate the risks within the early warning notices.
Compensation events were raised within 4 weeks that we became aware of an event, a contract amendment by the Holcim UK. Similarly to early warning notices, the commercial team would contact the Holcim UK’s project manager to discuss any potential compensation events with the Holcim UK’s project manager prior to submission. The commercial team then had weekly commercial meetings with the Holcim UK to agree the compensation event. Once the compensation event was agreed, the Holcim UK would request us for a quote for the compensation event, which would include cost and time impact. Once quoted, we would agree the quote within our minuted weekly commercial meetings.
The Holcim UK specified the use of CEMAR to administer the contract due to its compliance with supporting the NEC suite of contracts. To manage the contract we used CEMAR for key tasks including;
We'd love to hear from you, so please get in touch